Due to Riverview construction, there will be a detour of cart and pedestrian traffic to the paved path leading to the wooden bridge from Reynosa Drive to De La Cruz. The temporary path will be open on May 9, 2022, pending construction plans.

Please see the schedule for the construction of the temporary cart path, as listed below:

May 5, 2022:               Pave path on Thursday, May 5

May 5, 2022:               Relocate chain link fence

May 9, 2022                Open the temporary path to the public and shut down the old path

May 13, 2022:             Safety signs installed